top of page

RESTORATION WORKS

The last scheduled train, before the work began, left Kidderminster for Bridgnorth at 16:40 on Saturday 28th December 2019.

FSV%20Ballast%20removed_edited.jpg

Layer by layer the viaduct fill was removed starting with the ballast, and followed by the stones underneath the track, to uncover the original waterproofing.

To repair the waterproofing, panels of fibre-reinforced concrete were cast over the arches, then expanding sealing strips were placed between the panels and against the side walls.

FSV 20200127 (9) laying the concrete.JPG

Nearly 3,000 tonnes of stockpiled fill was put back in and then on top of that was the ballast. On the south side, concrete troughs were laid for signalling cables.

Volunteers and the permanent way team started lifting the track on Monday 30th December 2019 to prepare the site for Walsh Construction.

SVR%20team%20removes%20track%20from%20Fa
FSV 20200110 (11)  gas main.JPG

In January 2020, whilst removing the layers, a live gas main was found and careful hand excavation was undertaken.

Leoseal on arches 0220.jpeg

Concrete fillets were then placed along both sides to keep the water from seeping out and two coats of special paints, or ‘Black Jack’ was put over the concrete walls. Finally, concrete was poured in to the structure covered with a layer of chippings.

Phase One Complete

2020 05 21 FSV Mortar Raking photo 1 by
Rope Work September Credit Jane Preece.j
20200901 FSV GRP.JPG

On Monday 18th May 2020 work started on repairing the brickwork. The team from CAN started by raking out and re-casing the bricks.

_IMG9547.jpg

Everything was going well until a bat was seen flying out from one of the arches in June! All work came to a halt as a license was obtained from Natural England.

On Monday 20th July 2020 work finally restarted on repairing the brickwork after a license was obtained. Once again workers were seen dangling off the side of the viaduct from ropes.

In November 2020 decorative brick corbelling is added to the viaduct, although appearances can be deceptive. Despite looking exactly like brick, the corbelling is in fact made of glass reinforced plastic, or GRP.

20201119 FSV Copings (14).JPG

Four capping stones carved by the SVR’s stonemason Philip Chatfield were lifted into place on the Bewdley end of Falling Sands Viaduct on Thursday 19th November. The stones were originally from a redundant viaduct in Manchester.

20201214 FSV (31).JPG

Just a few weeks later than planned, and despite setbacks from Covid-19, bats and a live gas main, the final panels of GRP were attached and the work was completed on Thursday 10th December 2020.

Phase Two Complete

  • White Facebook Icon
  • White Instagram Icon

Follow us on Instagram

bottom of page